Housing scheme under CGEWHO : Status




» »



03 Feb, 2010 7:18p.m.

The present status of housing schemes to provide houses to the Central Government employees under Central Government Employees Welfare housing Organisation (CGEWHO) in different parts of the country is as follows. The position was reported to the Ministry of Housing and Urban Poverty Alleviation (HUPA) by the Central Government Employees Welfare Housing Organisation (CGEWHO).

According to CGEWHO Houses are under construction in the following schemes:

style='width:318.2pt;margin-left:5.4pt;border-collapse:collapse'>











































Sl.


No.



Scheme



Scheduled date


of completion


 



Expected date of completion



1.



Chennai
Phase-II



14.12.2009



September,
2010



2.



Hyderabad style='font-size:10.0pt;font-family:"Arial","sans-serif"'>  style='font-size:10.0pt;font-family:"Arial","sans-serif"'>Phase-III



21.12.2009



December,
2010



3.



Bhubaneswar style='font-size:10.0pt;font-family:"Arial","sans-serif"'>Phase-I



05.04.2011



December,
2010



4.



Mohali  style='font-size:10.0pt;font-family:"Arial","sans-serif"'>Phase-I



29.01.2011



December,
2010



5.



Meerut  style='font-size:10.0pt;font-family:"Arial","sans-serif"'>Phase-I



11.04.2012



August,
2011



6.



Jaipur  style='font-size:10.0pt;font-family:"Arial","sans-serif"'>Phase-II



07.06.2011



March,
2011






According to CGEWHO Housing scheme at Vishakhapatnam has been announced and construction on this project to be commenced on approval of plans by Statutory Authorities. There is no project as on date in Delhi, Gurgaon and Noida.


The above mentioned housing schemes under construction are progressing as per schedule mentioned against each except the Chennai Phase-II and Hyderabad Phase-III Schemes for unforeseen reasons such as additional requirement of provisioning of about 3000 pile foundations in the case of Chennai Phase-II Scheme and delay in getting the approval of plans from the statutory authorities on account of litigation in respect of Hyderabad Phase III Scheme.

Houses under all the above mentioned 6 schemes under construction have already been allotted. The Executive Committee and the Governing Council of CGEWHO periodically meet to discuss the issues pertaining to CGEWHO including monitoring of its functioning.


Dont forget to share this post
Post to facebook Tell your friends

Enter your email address for latest Staff News:

Other General News

Other News

Govt. Job openings.

Join the Employees community. Receive all updates via Facebook. Just Click the Like Button Below...

Facebook Gconnect
Social Reading at Staffcorner